Complete Project

The Fairfield to Congress Substation Transmission Line represents the final phase of a larger project to rebuild UI’s transmission lines along the 25 miles of the Metro North Railroad(MNR) corridor between Fairfield and West Haven. In total, there are 5 phases to the project (click dropdown arrow next to a phase to display related details):

Phase 1: Baird to Congress Substation (Petition 1176) COMPLETED

Location: Stratford to Bridgeport

Project Overview:  replace the existing bonnets with new tubular steel monopoles for both lines between the existing Baird Substation (Stratford) and existing Congress Substation (Bridgeport) , for a total distance of approximately 2.3 miles 

Timing: 

Easement Requirements:  Yes, but can't find acreage

Vegetation Clearing:  Yes, but can't find acreage

Documents


Phase 2: Housatonic River (Petition 1138) COMPLETED

Project Overview:  replace the existing bonnets with tubular steel monopoles for both lines that cross the Housatonic River from Stratford to Milford, for a total distance of 1 circuit mile

Timing: 

Easement Requirements:  Yes, to the Ashcroft and NRG properties, but can't find specific acreage

Vegetation Clearing:  Yes, can't find acreage but permanent impact appears to be minimal

Documents

Phase 3: HRX to Baird (Petition 1304) COMPLETED

Location: Stratford

Project Overview:  replace the existing bonnets with new tubular steel monopoles for both lines from the existing Baird Substation (Stratford) to just past the existing Barnum Substation (Stratford), for a total distance of approximately 1.9 miles 

Timing: 

Easement Requirements:  8.43 acres

Vegetation Clearing:  Yes, but can't find acreage

Documents

Phase 4: Milvon to West River (Docket 508) APPROVED

Location: Milford to New Haven

Project Overview9.5 mile transmission line rebuild between existing Milvon Substation (Milford) and existing West River Substation (New Haven)

Timing: 

Easement Requirements:  17.65 acres of permanent easements 

Vegetation Clearing: 28 acres in total, 22 of which will be permanent

Documents

Phase 5: Fairfield to Congress Substation (Docket 516) PENDING

Location: Fairfield to Bridgeport

Project Overview:  7.3 mile transmission line rebuild between Catenary Structure B648S just east of Sasco Creek (Fairfield) and existing Congress Street Substation (Bridgeport

Timing: 

Easement Requirements:  19.25 acres of permanent easements 

Vegetation Clearing: 6.5 acres in total, 5.5 of which will be permanent

Documents